问题描述:
英语翻译
A project scheduled to be carried out over a single fiscal year has a budget of 12600,divided into 12 equal monthly allocations.At the end of the fourth month of that fiscal year,the total amount actually spent on the project was 4580.By how much was the project over its budget?
A project scheduled to be carried out over a single fiscal year has a budget of 12600,divided into 12 equal monthly allocations.At the end of the fourth month of that fiscal year,the total amount actually spent on the project was 4580.By how much was the project over its budget?
问题解答: