问题描述:
英语翻译
Spindle orientation dog seat installation
Spindle shaft fix the 10x8x25 double round key,then install the orientation dog seat (block),then fix the setting screw.
Drawbar installment
1.Smear the grease on the Spring Disc.
2.Collet (normally is 4-petal) fixes on the drawbar
3.Put 3 pcs (as one team) of Spring Disc to the bottom of drawbar and the concave face down (outside),then use the 3 pcs as one set,and the each set (3 pcs) back to back and face to face put the Spring disc to the drawbar.The total is 114 pcs (normally 114 pcs,but some of spindle is different).
4.After finished the drawbar spring disc alignment then fix the spring disc stopper,and turn in let the spring disc total length to the standard length (114pcs about 277mm),then the drawbar top fix the M16x1.5 nut.
Spindle's tension force (pull/push force) & Runout inspection and test
1.Put in the drawbar to the spindle shaft center hole.
3.Put the spindle on tension force platform,and test the spindle tension force with tension meter (guage) and the tension force about 1000±100kgs.
4.If the tension force too large or too small that can adjust the drawbar's length.(FV1200/1500 BT-50 the tension force is 1500kgs ± 100kgs)
5.Finish above job then fix the nut.
6.Clamp the 300mm test bar and measure the 300mm place (end) the spindle test bar runout,the runout variation could not exceeding 0.01mm.
Spindle sleeve and front cover assembly
1.Refer to the above calibrated distance (value) and Grinding the front cover for the spindle bearings' preload.The preload value is 0.03mm.
2.Put in the spindle sleeve and fix the front cover,then finish the installation.
Spindle Dynamic balance
1.According the Dynamic balance machine operational manual operates the balance machine for adjust the balance.
Spindle temperature warm up test
1.After spindle balance adjustment then put on the running test platform for doing the temperature warm up test.
Spindle orientation dog seat installation
Spindle shaft fix the 10x8x25 double round key,then install the orientation dog seat (block),then fix the setting screw.
Drawbar installment
1.Smear the grease on the Spring Disc.
2.Collet (normally is 4-petal) fixes on the drawbar
3.Put 3 pcs (as one team) of Spring Disc to the bottom of drawbar and the concave face down (outside),then use the 3 pcs as one set,and the each set (3 pcs) back to back and face to face put the Spring disc to the drawbar.The total is 114 pcs (normally 114 pcs,but some of spindle is different).
4.After finished the drawbar spring disc alignment then fix the spring disc stopper,and turn in let the spring disc total length to the standard length (114pcs about 277mm),then the drawbar top fix the M16x1.5 nut.
Spindle's tension force (pull/push force) & Runout inspection and test
1.Put in the drawbar to the spindle shaft center hole.
3.Put the spindle on tension force platform,and test the spindle tension force with tension meter (guage) and the tension force about 1000±100kgs.
4.If the tension force too large or too small that can adjust the drawbar's length.(FV1200/1500 BT-50 the tension force is 1500kgs ± 100kgs)
5.Finish above job then fix the nut.
6.Clamp the 300mm test bar and measure the 300mm place (end) the spindle test bar runout,the runout variation could not exceeding 0.01mm.
Spindle sleeve and front cover assembly
1.Refer to the above calibrated distance (value) and Grinding the front cover for the spindle bearings' preload.The preload value is 0.03mm.
2.Put in the spindle sleeve and fix the front cover,then finish the installation.
Spindle Dynamic balance
1.According the Dynamic balance machine operational manual operates the balance machine for adjust the balance.
Spindle temperature warm up test
1.After spindle balance adjustment then put on the running test platform for doing the temperature warm up test.
问题解答:
我来补答展开全文阅读